Commissioners clarify sewer moratorium

Dec 11, 2020

Guy Campinha, the head of the town’s sewer department, clarified the moratorium on new sewer connection’s at the commissioner’s Thursday night meeting.

Homes and businesses with an existing sewer connection — even one that hasn’t been used in years — are excluded from the moratorium as those flows have already been accounted for.

Campinha said that also goes for buildings that had connections and were demolished before being rebuilt.